2024 Street Improvements Project

To whom it may concern-  

 As part of the 2024 Street Improvements Project, the City of East Gull Lake has contracted with Anderson Brothers Construction to perform construction on Pine Beach Peninsula and Birch Grove Road. 

 Pine Beach Peninsula 

  • Pine Beach Peninsula is receiving a mill and overlay from the intersection of Pine Beach Rd (CSAH 77) to Madden’s Parking Lot.
  • Construction in this area in anticipated to start May 14th to May 16th and striping is anticipated to occur on June 4th.
  • The street will be open during construction, however access to properties will be limited and minor delays should be expected. 

Birch Grove Road 

  • Birch Grove Road is receiving a removal and replacement of one sanitary sewer manhole, potentially two new sewer service connections to properties, and an overlay of the street from 10172 Birch Grove Road to the Dead End. 
  • Construction in this area is anticipated to start May 22nd and finish on May 30th 
  • The street will be closed during the removal and replacement of the sanitary sewer manhole and potential installation of two new sewer service connections to properties on the south side of Birch Grove Road. This work is scheduled for May 22nd to May 24th and will only affect properties west of 10074 Birch Grove Rd. 
  • Following the utility work listed above, an overlay of the road will take place from May 28th to May 30th .  During this time the street will be open, however access to properties will be limited, and minor delays should be expected. 
Any questions regarding this project should be directed to Grace Liljenquist, Project Inspector with WSB LLC, at 612-708-7281. We appreciate your patience at this time as we work to improve our city streets.